Ⅲ. Labor Organizations and the Deployment Plan of the Task
(I) The Arrangements for the Staff
For the tight schedule of the project, the staffing considerations are adequate. The total number of personnel in Project Manager Department is 40 and the total number of workers is 2130 in all the construction teams. 2170 people will be in the site under dynamic management.
(Ⅱ) Task Assignment
According to the project characteristics and schedule requirements, the staffing considerations are adequate. Three subgrade construction teams, four bridge and culvert, two pile professional, three beam of professional, three tunnels professional are proposed. The total number in Project Manager Ministry is 40 and 2130 (including management services staff) in the construction team. 2170 people would be in the site, using active management. The task partition is showed in the “District Task Assignment Table”
The District Task Assignment Table
Name of teams Number Districts division Length of districts(km) Main workload
Subgrade construction teams No.1 120 K93+650~K94+500 0.85 All the subgrade excavation and fill construction (including connecting line) in the district
Subgrade construction teams No.2 120 K94+500-K99+000 4.5 All the subgrade excavation and fill construction in the district
Subgrade construction teams No.3 100 K99+000-K104+800 5.8 All the subgrade excavation and fill construction in the district
bridge and culvert team No.1 200 K93+650~K94+500 0.85 All the constructions of bridge and culvert, protection and drainage project in the district(including connecting line)
bridge and culvert team No.2 240 K94+500-K99+000 4.5 All the constructions of bridge and culvert, protection and drainage project in the district
bridge and culvert team No.3 150 K99+000-K104+800 5.8 All the constructions of bridge and culvert, protection and drainage project in the district
Pile team No.1 100 K93+650~K98+000 4.35 All the piles in the district
Pile team No.2 100 K98+000~K104+800 6.8 All the piles in the district
Tunnel team No.1 200 1.7777 Tunnel of No.1、2、3 in Tianlin
Tunnel team No.2 300 4.352 Tunnel of No.4、5 in Tianlin
Tunnel team No.3 200 1.94 Tunnel of No.6、7 in Tianlin
Beam team No.1 100 K93+650~K94+500 0.85 All the prefabrication and fixing of bridge and culvert in the district
Beam team No.2 100 K94+500-K99+000 4.5 All the prefabrication and fixing of bridge and culvert in the district
Beam team No.3 100 K99+000-K104+800 5.8 All the prefabrication and fixing of bridge and culvert in the district
Section 3 Material Organizations and Supply Plans
Ⅰ. The O