Technical Proposal
The Site Organization
The General Plane Chart of the Construction Site
Contract No. 6
Combined the eternal with the temporary construction facilities, the layout of construction and the choosing of the construction blueprint should be consistent under the premise of meeting the needs of the production and life of construction. All aspects should be concerned so as to make a rational layout.
Based on the construction features and the reality of the fieldwork as well as our company, the general layout should be made according to the principles as follows:
1. Economical Principle. The temporary and the eternal construction should be combined. In certain circumstances, less farmland should be occupied. The facilities which can be improved or renewed by using local facilities should not be rebuilt.
2. Convenient Principle. The convenience of entering and exiting the construction place should be improved, and disturbance of the construction should be lessened. It is advisable to make full use of the local resources, for it is very convenient of contacting.
3. Managing-oriented Principle. The construction should be easily managed. The labor and the construction equipments should be easily allocated. The disturbance of the construction should be easily lessened. The construction should be built in a civilized way.
4. Secure Principle. The transportation security should be ensured. The side effect on the transportation caused by it and other construction project in the same period should be reduced. The construction should be easily done in the monsoon and flood season. The standard working place should be easily built.
If you want to see the temporary working plan, please refer to the “Chapter 5” in the Certification on the Construction Methods.
The details of the general layout blueprint of the section bid at this phase can be seen in the “General Plane Chart of the Construction Site”.
Method Statement
Description in Words of Construction Organization Design
Chapter 1 The Compiling Statement of Construction Organization and the Construction Schemes
Section 1 The Compiling Statement of Construction Organization Design
I. The Reference Materials of Compiling:
(I) The procurement document of the project of constructing Longlin to Baise Expressway Project Civil Works and the relevant requirements at the conference before the bidding.
(II) The designing paper, documents, and materials made by Chongqing Transportation Designing Institute and provided by the procurer c